New machinery installation - update
Friday 15th July
All five machines now fully operational. We now have more capacity than we have ever had and it gives us the opportunity to catch up and then push forward with our sales guys chomping at the bit!
Thursday 14th July
Both new machines now up and running, problem is one of our older machines has been down for three days with an unknown problem. Engineers are trying to establish fault.
Monday 11th July
The 3040 is now up and running and it, hopefully, will not be long now until the 3030 is running too. By that time we will have more capacity than we have ever had, that should keep the sales guys quiet for a while. David Cave (photography) has been in to take some photos before the machines start to show signs of use.
Friday 1st July
All pieces of equipment have now been placed in their final positions, levelled and bolted down. Visually everything is now as it will be on completion. All that is required now is to complete the myriad of connections for power, water, gases and controls. we are hoping to have both machines up and running by next Friday.
Thursday 30th June
14.00hrs
All equipment in place and ready for connections. Trumpf personnel and electricians in attendance. the whole installation is starting to look something special. It is amazing how much space the mezzanine floor is going to save. it looks as though, ultimately, we will be able to get six machines where we presently have five, and still have more free floor space.
Wednesday 29th June
10.30hrs
10.00hrs The two new machines have arrived and are being unwrapped on the lorries. Engineers are in attendance to begin installation. The worst part of the whole process, for me, is about to happen - seeing half a million pounds worth of equipment swinging about on the end of a crane is not nice!
Monday 27th June.
Transport on site to remove older 3050. Everything back on schedule now and we have the rest of the day and all day Tuesday to have a clean up before the new machinery arrives on Wednesday.
Saturday 25th June.
Traditional Structures Ltd on site to install mezzanine floor. Slight issue concerning position of ladder but other than that all went well - a great job.
Friday 24th June.
Still encountering delays with moving middle 3050 but, by lunchtime, couldn't wait any longer to begin decommissioning of older one. by evening machine is decommissioned and moved far enough to enable installation of mezzanine floor.
Thursday 23rd June
Should be decommissioning old L3050 but delays in moving second L3050 mean we cannot lose another machine just yet. A lot of rescheduling going on and we should be back on target by Friday night. One bonus with not completing move of 2nd 3050 until tonight is that we have the other available overnight. That means Simon can sleep a little easier and Marcus, after the day he has had, will probably get drunk!
Wednesday 22nd June
Engineers in to move L3050 cabinets, a day later than expected. Fortunately we have left a buffer between the time allowed to remove old equipment and the delivery of the new. It looks as though we may need it! We are desperately trying to hold on to schedule but not helped by unexpected outside influences.
Monday 20th June
Engineers in attendance to sort out ventilation issues on L3050 prior to moving its ancillary equipment to a new configuration. This is to create sufficient space for new L3030.